Construction has reached the top floor, marking a significant milestone. Now, the contractor is focusing on completing the exterior shell of the building and framing and finishing the interior.
November was another busy month at City Hall, and crews continue to make significant progress.
Here is a list of some of the work crews have performed in the last month.
The last beam was set, and the topping out party was on Nov. 7.
Crews have framed in the tower floors up to level 13.
The elevator steel is installed up to level 15.
Both internal stairs are complete.
The penthouse steel is being installed.
Precast installation continues.
Interior caulking of windows is ongoing.
Installation of and caulking of the glass on levels one through three continues.
The terrace planter walls on level two were poured.
Installation of elevators nine and ten is ongoing.
Drywall installation on levels one and two has begun.