Please say that you mean that they “are” doing this? Or you hope that they will do this?
Sorry to be a pain but I am a tree hugger and it’s hard enough to get trees much less keep older trees…please and thank you
The plans have 5 trees on Hillsborough St. being protected to save.
Fencing around the perimeter is going up now.
301 Hillsborough St. will apply for their permits the first of October .
This is the building permit to actually start construction?
Thank you for the update. But I am sooooooooooooooooo confused!
I was under the impression from all the above on this thread that they are already starting construction? What is this about “more” permits? I mean, really…w.t.h.
They have started… the protective fencing is being put up.
They don’t have a building permit yet. They do have a grading permit which allows them to start sitework. There are a couple of other permits that are approved and waiting for issuance. They have already submitted for the building permit, but it has not yet been approved.
Developer can not get his building permits until recombination plat done to combine all tracts into one . Council on Tuesday has to approve encroachment & Developer is ready to roll !
Wow…so just how many years does it take to actually get shovel ready?
Exectly eleventy years.
When is the actual structure going to begin?
Looks like they are still just operating under a land disturbance/grading permit. Someone can confirm but last I heard building permit was still under review
Jeez they’re never going to get this through honestly
It looks like they failed their express review on the 4th. Someone is not making the corrections they need to make.
Looks to be mostly cleared off. Only activity I could see was an electrician working on the boxes in the back of the lot (have to zoom in real close to see)
That old house is still there… wondering if they’re planning to move it/save pieces of it like that old house on the Bloc 83 parking deck lot…
It’s on the other side of the fencing… maybe it is not part of this particular phase of Raleigh Crossing?
Correct. Its in Phase 2. However the developers hinted that Phase 2 would be starting in the Spring?