Edit: I’ll answer my own question. It seems to be a bunch of trusses that have been piled up on the top floor. I wonder how they fit into this, though. I assumed it would be all standard concrete slabs with the little temporary supports underneath until they’re set.
They will use those use “trusses” as part of their shoring and forming for the next slab. They will build what they call it “concrete tables” which makes the forming and concrete pouring process faster and this will help cut the schedule by 30%-40%.
Third floor framing has already begun, this building makes a serious impact when driving down Dawson st.
I can’t wait for it to begin appearing over the train tracks and see it’s full impact height.
Fairview ground floor is probably level with where that building is at now… compared to the self storage beside it - I’d say floor 6-7 is when it’ll really become visible in all directions?